Just so you know, we have not dropped off the face of the Earth here. Suffice it to say that The Fuzz has been busy elsewhere. But now for the exciting part. Our Fuzz has taken this week off from the garbage business to work on the Shed Project!
Last week he made arrangements to have the tin delivered. As you can see below, it is here.
But when he saw it (he was not home for the delivery) he noticed* a discrepancy. Although he had ordered 10' tin, here we see 12' tin!
But the design (and framing) calls for 10' metal up there.
On consideration, it was thought that extending the eaves the extra 2ft, could provide some useful sheltered space to store garden tools and such out of the weather. So our Adaptable Fuzz picked up some materials to add some light extensions to this roof.When it gets light, and he has finished this post, The Fuzz will get started on this. We will attempt to keep y'all informed on the progress of this exciting project.
*This was discovered by noting the difference between the 10' ridge pieces, and the 12' stuff!